Plot No.9 - Ready for occupation
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.10 - Brick Work Completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.11 - Brick Work in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.12 - Plastering Completed
Nov 2011 |
|
|
|
| |
|
|
| |
|
|
| |
 |
Plot No.14 - ,Foundation completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.21 and 22 - Plastering in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.24 - Ready for Occupation
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.25 -Brick Work in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.26 - First Floor in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.27 - Plastering in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.28 -Brick Works in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.29 - First Floor Roof Completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.30 - First Floor Roof Completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.31 -Brick Work in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.32 - Foundation Completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.34 - Ground Floor Roof Completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.35 - Plastering in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.37 - Tileing Work in Progress
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.39 & 40 - Tileing works Completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No.41 & 42 -Tileing Works Completed
Nov 2011 |
|
|
|
| |
|
|
| |
 |
Plot No. 43 & 44 - Brick Works Completed
Nov 2011 |
|
|
|
| |
|
|
| |
|
|
| |
|
|
| |
 |
Plot No.48 - Foundation Completed
Nov 2011 |
|
|
|
| |
|
|
| |
|
|